Under Design

Knights on Big Bay – Barrie, Ontario

Knights on Big Bay

Barrie, Ontario

Disclaimer: All renderings are the artist’s concept. Materials, specifications, and architectural details are subject to minor modifications. E&OE. (Renderings may show upgraded packages; additional packages are available.)

Listing Highlights

Prime Location

Convenient access from Ashford Drive and Montgomery Drive

Parking & Accessibility

32 surface parking spaces and 329 underground spaces for residents’ convenience

Zoning Upgrade

A shift from ‘Single Detached Dwelling First Density’ (R1) to ‘Residential Apartment Dwelling Second Density’ (RA2) with Special Provisions, allowing for reduced parking, setbacks, landscaped open spaces, and increased lot coverage

Community-Oriented Living

Thoughtfully designed units, shared community spaces, and a variety of amenities

Affordable Housing Options

Proposed affordable units to support diverse housing needs

King on Yonge First Building
King on Yonge First Building Side View
King on Yonge Second Building Side View
King on Yonge Second Building Side View

Property Overview

Introducing The Gold Knight and The Onyx Knight

Midnight presents The Gold Knight and The Onyx Knight! Two purpose-built, mid-rise buildings designed with our signature focus on self-reliant, community-driven living. Located just steps from Painswick Park and top-rated schools, these towers bring 456 new rental units to Barrie’s growing market. As part of a larger four-tower masterplan, they anchor the front of the development along Big Bay Point Road, setting the tone for a vibrant, connected community.

For more information, click here

Development Process

1

Site Acquisition

Application Submission for Pre-con

March 10, 2024 submitted

2
3

Pre Consultation Meeting

August 1, 2024

Neighborhood Consultation Meeting

October 10, 2024

4
5

First Formal Rezoning Submission

November 22, 2024

Notice of Completion from City

Received Jan 2, 2025

6
7

Public Meeting

May 28, 2025

General Committee - City Staff Report circulation

June 09, 2025

8
9

Council Vote

June 18, 2025

Appeal period

20 days from day of approval for zoning to reflect on govt records

10
11

Site Plan Application (Target)

August15, 2025

Conditional permits running concurrently

12
13

Groundwork/ excavation

Fall (starting August/ Sep 2025)

Above grade Construction

Aim to begin late 2025

14